MIL-DTL-24640C
TABLE XIV. Sampling for group A examination and tests.
Units of product in lot
Number of samples
1
1
2 thru 10
2
11 thru 30
3
31 thru 90
7
91 thru 210
15
211 and over
25
4.4.3.2 Sampling for group B tests. Samples for Group B tests shall be selected from each lot as specified in
table XV.
TABLE XV. Sampling for group B tests.
Units of product in lot
Number of samples
8 and under
1
9 thru 30
2
31 thru 90
3
91 thru 210
4
211 and over
5
4.4.3.3 Sampling for group C tests. Samples for Group C tests shall be selected as specified in table XVI.
TABLE XVI. Sampling for group C tests.
Two month's production (units of
Number of samples
product)
8 and under
1
9 thru 30
2
31 thru 90
3
91 thru 210
4
211 and over
5
4.4.3.4 Sampling for group D tests. Samples for Group D test shall be selected by testing the first production
run of each type and size of cable each calendar year (20xx) (see 6.2.5).
4.4.3.5 Sampling, accept/reject criteria. Material found unacceptable shall be resubmitted for reinspection only
after all materials are re-examined or re-tested or both (re-examined and re-tested) and all defective materials are
removed or defects corrected. Material resubmitted shall be verified 100 percent for the failing characteristic.
Material found acceptable during rescreening inspection/testing can be re-identified and released as a separate lot.
4.4.4 Group A examination and tests. Group A examination and tests as required by the specification sheet
shall be performed on samples selected in accordance with 4.4.3.1.
20