MIL-DTL-10392F
TABLE VI. Group A inspection.
Examination or test
Requirement paragraph
Test method paragraph
Subgroup I
Visual and mechanical
Material and construction
Workmanship
Subgroup II
Electrical
Dielectric withstanding voltage
Insulation resistance
Conductor resistance
4.4.2.3 Rejected lots. Failure of a lot to pass any test or inspection constitutes failure of the lot and
the lot shall be rejected. If an inspection lot is rejected, the contractor may rework the lost to correct the
defects, or screen out the defective units and resubmit the lot for re-inspection. Such lots shall be
segregated from new lots and shall be identified as re-inspected lots.
4.4.3 Group B inspection. Group B inspection shall be performed on inspection lots that have
passed group A inspection and on specimens selected from units of product that have been subjected to
and met the group A inspection. Group B inspection shall include the applicable inspections specified in
4.4.3.1 Order of inspection within group B. Group B inspection shall be performed in any order which
is satisfactory to the government.
4.4.3.2 Disposition of samples. Samples subjected to group B tests shall not be included as part of
the delivered product.
TABLE VII. Group B inspection.
Examination or test
Requirement paragraph
Test method paragraph
Subgroup I
n/a
n/a
Conductor strands
n/a
n/a
Tin coating
Tensile strength and elongation
Conductor strand resistance
Subgroup II
n/a
n/a
Cord
n/a
n/a
Conductivity of fibers and yarns
Tensile strength
Flexing life
Subgroup III
n/a
n/a
Insulation and jacket
n/a
n/a
Cold bend
4.5 Test methods.
4.5.1 Visual and mechanical inspection. The finished cords shall be given a visual and mechanical