MIL-DTL-38359E
TABLE IV. Group B inspection.
Inspection
Requirement paragraph
Method paragraph
Moisture absorption
Ozone resistance test
Cold bend test
Insulation resistance test
Insulation thickness test
Wire resistance test
Physical properties test
High temperature test
4.4.4.1.1 Inspection lot. An inspection lot shall consist of all cables of the same type designation (see
1.2.1) produced under essentially the same conditions and offered for inspection at the same time.
TABLE V. Inspection sample.
1/
Production lot size
Sample size
2 to 8
2
9 to 15
3
16 to 25
5
26 to 50
8
51 to 90
13
91 to 150
20
151 to 280
32
281 to 500
50
501 to 1200
80
1201 to 3200
125
3201 to 10000
200
1001 to 35000
315
1/ Lot size will be based on number of reels, spools or coils of product.
TABLE VI. Small sample inspection.
Lot size (passed group A
Sample size
inspection)
2 to 25
2
26 to 150
3
151 to 1200
5
4.4.5 Group B acceptance. Each sample selected in accordance with 4.4.1.1 shall be examined to
determine conformance with the requirements in table V. If one or more defects are found in the
inspection sample, the production lot shall be rejected and shall not be supplied to this specification.
Group B inspections may be performed in any order acceptable to the government.
4.4.6 Disposition of sample units. Samples subjected to group B tests shall not be delivered on
contract or order.